Agency Wide – All Districts Project Update
October 7, 2022Participation Program Policy Updates: The Agency is preparing updates to its Participation Program policy for the Board’s consideration at its October 10, 2022 meeting. Updates address the Agency’s practice of continually improving the program, opportunity to assist with projects anticipated to be complete within 24 months of a district’s sunset, and better support the City’s priority to assist in the creation of attainable housing. The updates include the creation of a unique policy for the State Street District allowing the Agency to better support transit-oriented projects in its unique development context. Project Leads: Alexandra Monjar, Kevin Holmes, and Doug Woodruff
Parking & Mobility |
Boise Bike Share 2.0: The Agency Board approved a sponsorship agreement for the Bike Share 2.0 pilot program at the June Board meeting. Valley Regional Transit launched the pilot program starting with 50 bikes on July 13. From July 13 through August 31, users have taken 1,256 rides on the bikes. through the September 1 deadline for matching sponsorships, Valley Regional Transit has secured $25,000 in sponsorships from other organizations. Project Lead: Matt Edmond
ParkBOI – Garage Stairwell Handrails: Cascade Enterprises will be removing out of compliance handrails and cable guards and refabricating, painting, and reinstalling new ones in the 9th & Main, 10th & Front, Capitol & Main, Capitol & Myrtle Garages, site work is complete at the 10th & Front garage. The stairwell landings, stairs and lips at the 10th & Front Garage have been painted as of September 30. Removal and fabrication of the hand and guardrails has started at the Capitol & Main garage main street side tower painting of the rails is in progress. Removal and fabrication of the handrails has begun at the 9th & Main Garage main street side tower. The project contract amount is $406,000. Project Lead: Aaron Nelson
421 N 10th St Property- Atlas will be conducting site walks for the demo inspection in September. The Agency is working on an agreement with the Carpark on monitoring the lot. Project Lead: Aaron Nelson
ParkBOI – 10th & Front Garage – Stairwell Enclosure: Guho Corporation enclosed the stairwells with storefront windows to prevent weather damage and water infiltration. Enclosure and painting work completed in June. Lighting upgrades inside the stairwells were completed in September. The project estimated cost is $99,000 and is now complete. Project Lead: Aaron Nelson
City GO: Formerly known as the Downtown Mobility Collaborative, the downtown’s Transportation Management Association is up and running. This partnership of Valley Regional Transit, City of Boise, ACHD Commuteride, Boise State University, St Luke’s Hospital, Downtown Boise Association, and CCDC involves marketing its transportation products and services to the downtown community. The CCDC Board approved a renewed Memorandum of Understanding for City Go at its October 2020 meeting. In response to a request from VRT, the Agency has included a $60,000 contribution to City Go in the proposed FY2022 budget for CCDC. An overview is located at citygoboise.com. Project Lead: Matt Edmond
ParkBOI – 9th & Main Garage, Capitol & Main Garage Waterproofing: Construction started the second week of July, with estimated completion to be at the end of August. The project is now in the closeout phase. Water ponding added to the project to fix low spots to help drainage at the Capitol & Main Garage. Contract amount is $57,000. The contract amount is $417,592. Project Lead: Aaron Nelson
Condominium Associations |
Building Eight Condominiums Association
CCDC Contact: Aaron Nelson |
||
Member | Unit | Percent Interest |
CCDC | Capitol & Myrtle Parking Garage (Unit 2) | 35% |
Raymond Management | Hampton Inn & Suites (Unit 1) | 62.5% |
Hendricks | Retail Units (Units 3 & 4) | 2.5% |
Condo Board Meetings | ||
Last Meeting | Next Meeting | Next Report Due |
December 20, 2021 | December 2022 | December 31, 2022 |
Issues/Comments: | The Agency is working on expanding EV charging stations to all garages this calendar year. |
Front Street Condominium Association
CCDC Contact: Aaron Nelson |
||
Member | Unit | Percent Interest |
CCDC | 9th & Front Parking Garage | 25.76% |
GBAD | 2.00% | |
Aspen Condominiums | Aspen Lofts | 52.17% |
Hendricks | BoDo Retail Units | 20.07% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
September 20, 2022 | TBD | November 30, 2023 |
Issues/Comments: | Annual meeting held Sarah from EPR will be having some roof work done on one of the stair towers to prevent water from infiltrating the tower. |
U.S. Bank Plaza Condominium Association
CCDC Contact: Matt Edmond |
||
Member | Unit | Percent Interest |
LN City Center Plaza/ Clearwater Analytics | A, 1A, 1B, 1C, 1H, 1K, 1L, 2C, 3C, 5A, 6A, 7A, 8A, 9A | 77.372% |
CCDC | 1F, 1G, 1J, 2B, 4B, 5B | 6.861% |
GBAD | 4A | 3.040% |
Boise State University | 1D, 1E, 2A, 3A, 3B | 6.131% |
Valley Regional Transit | B1, B2, B3 | 6.429% |
Sawtooth Investment Mgmt
|
10A | 0.167% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
July 23, 2021 | October 17, 2022 | August 2022 |
Issues/Comments: |
Capitol Terrace Condominium Association
CCDC Contact: Aaron Nelson |
||
Member | Unit | Percent Interest |
CCDC | Capitol & Main Parking Garage | 50% |
Hawkins Companies | Main + Marketplace | 50% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
October 26, 2021 | October, 2022 | October, 2022 |
Issues/Comments: | Meeting held October 26. Shayna Cox informed the Agency a new trash compactor in the trash room and a recycler for cardboard to be installed. |
Downtown Parking Condominiums Association
CCDC Contact: Aaron Nelson |
||
Member | Unit | Percent Interest |
CCDC | 9th & Main Parking Garage | 93.51% |
Les Bois Holdings, LLC | Commercial, Main Street side | 2.03% |
Eastman Building, LLC | Commercial, Idaho Street side | 4.46% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
September 28, 2022 | September 2023 | September 30, 2023 |
Issues/Comments: | Annual meeting was held, all parties were notified that the waterproofing project is now complete, the Handrails guardrails replacement project is currently going on and is anticipated to be done in December. |
ACME Fast Freight Condominium Association
CCDC Contact: Matt Edmond |
||
Member | Unit | Percent Interest |
CCDC | 11th & Front Parking Garage, 30.1%
(Units 402, 403, 501, 502) |
28.485% |
Ball Ventures Ahlquist | 11th & Front Parking Garage, 69.9%
(Units 104, 015, 201, 202, 301, 302, 401) |
66.490% |
Boise Metro Chamber | Boise Chamber Offices
(Units 101, 102, 203) |
5.025% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
January 3, 2022 | TBD | TBD |
Issues/Comments: |