Agency Wide – All Districts Project Update

January 9, 2023

News & Notes

 

Parking & Mobility

Boise Bike Share 2.0: The Agency Board approved a sponsorship agreement for the Bike Share 2.0 pilot program at the June Board meeting. Valley Regional Transit launched the pilot program starting with 50 bikes on July 13. From July 13 through August 31, users have taken 1,256 rides on the bikes. Through the September 1 deadline for matching sponsorships, Valley Regional Transit has secured $25,000 in sponsorships from other organizations. Project Lead: Matt Edmond

ParkBOI – Garage Stairwell Handrails: Cascade Enterprises will be removing out of compliance handrails and cable guards and refabricating, painting, and reinstalling new ones in the 9th & Main, 10th & Front, Capitol & Main, Capitol & Myrtle Garages, Removal and fabrication of the hand and guardrails completed at the Capitol & Main, 9th & Main garages. Idaho street side tower painting of the rails is in progress and will be complete the first week of December. Minor Fabrication of the handrails, guardrails has begun at the Capitol & Myrtle garage, the project reached Substantial completion on December 7, 2022, and is now in the process of closing out.  The project contract amount is $406,000. Project Lead: Aaron Nelson

EV Station Garage Project: Quality Electric will be installing EV stations in four CCDC/ParkBOI Garages (9th & Main, 10th & Front, 11th & Front Capitol & Myrtle) A single pole 2 charge system will be installed adding 2 charging spots per garage. Work is set to start in January. Project cost is $64,000. Project lead: Aaron Nelson

421 N 10th St Property: The Agency has an agreement with the Carpark to monitor the lot starting in November. Project Lead: Aaron Nelson

City GO: Formerly known as the Downtown Mobility Collaborative, the downtown’s Transportation Management Association is up and running. This partnership of Valley Regional Transit, City of Boise, ACHD Commuteride, Boise State University, St Luke’s Hospital, Downtown Boise Association, and CCDC involves marketing its transportation products and services to the downtown community. The CCDC Board approved a renewed Memorandum of Understanding for City Go at its October 2020 meeting. In response to a request from VRT, the Agency has included a $60,000 contribution to City Go in the proposed FY2022 budget for CCDC. An overview is located at citygoboise.com. Project Lead: Matt Edmond

10th & Front Garage Structural Concrete Repairs Phase 2

The Agency received board approval at the December meeting to award the contract to Consurco, the lowest bidder on this project. The scope of work consists of partial depth repairs on level four across the entire length of the beams, removal/replacement of concrete, installation of anodes and removal/replacement of any damaged rebar with epoxy coated rebar. The Agency’s budget includes sufficient funds and will start in the Spring of 2023. The contract amount is $790,997. Project Lead: Aaron Nelson

Condominium Associations

 

Building Eight Condominiums Association

CCDC Contact: Aaron Nelson

Member Unit Percent Interest
CCDC Capitol & Myrtle Parking Garage (Unit 2) 35%
Raymond Management Hampton Inn & Suites (Unit 1) 62.5%
Hendricks Retail Units (Units 3 & 4) 2.5%
Condo Board Meetings
Last Meeting Next Meeting Next Report Due
December 14, 2022 December 2023 December 31, 2023
Issues/Comments: Meeting was held and main topic of discussion was to update procedure in the event of another insurance claim. Power was lost to the Hotel due to an electrical issue; it has since been repaired.

 

Front Street Condominium Association

CCDC Contact: Aaron Nelson

Member Unit Percent Interest
CCDC 9th & Front Parking Garage 25.76%
GBAD 2.00%
Aspen Condominiums Aspen Lofts 52.17%
Hendricks BoDo Retail Units 20.07%
Condo Board Meetings
Last Meeting/Report Next Meeting Next Report Due
September 20, 2022 TBD November 30, 2023
Issues/Comments: Annual meeting held. Sarah from EPR will be having roof work done on one of the stair towers to prevent water from infiltrating the tower.

 

U.S. Bank Plaza Condominium Association

CCDC Contact: Matt Edmond

Member Unit Percent Interest
LN City Center Plaza/ Clearwater Analytics A, 1A, 1B, 1C, 1H, 1K, 1L, 2C, 3C, 5A, 6A, 7A, 8A, 9A 77.372%
CCDC 1F, 1G, 1J, 2B, 4B, 5B 6.861%
GBAD 4A 3.040%
Boise State University 1D, 1E, 2A, 3A, 3B 6.131%
Valley Regional Transit B1, B2, B3 6.429%
Sawtooth Investment Mgmt.

 

10A 0.167%
Condo Board Meetings
Last Meeting/Report Next Meeting Next Report Due
October 2022 TBD August 2023
Issues/Comments:

 

Capitol Terrace Condominium Association

CCDC Contact: Aaron Nelson

Member Unit Percent Interest
CCDC Capitol & Main Parking Garage 50%
Hawkins Companies Main + Marketplace 50%
Condo Board Meetings
Last Meeting/Report Next Meeting Next Report Due
October 25, 2022 TBD October, 2023
Issues/Comments: Stairwell work to be completed by December 2022. Fire inspection contract with JCI finalized.

 

Downtown Parking Condominiums Association

CCDC Contact: Aaron Nelson

Member Unit Percent Interest
CCDC 9th & Main Parking Garage 93.51%
Les Bois Holdings, LLC Commercial, Main Street side 2.03%
Eastman Building, LLC Commercial, Idaho Street side 4.46%
Condo Board Meetings
Last Meeting/Report Next Meeting Next Report Due
September 28, 2022 TBD September 30, 2023
Issues/Comments: The annual meeting was held, and all parties were notified that the waterproofing project is now complete. The Handrails guardrails replacement project is currently going on and anticipated to be completed in December.

 

ACME Fast Freight Condominium Association

CCDC Contact: Matt Edmond

Member Unit Percent Interest
CCDC 11th & Front Parking Garage, 30.1%

(Units 402, 403, 501, 502)

28.485%
Ball Ventures Ahlquist 11th & Front Parking Garage, 69.9%

(Units 104, 015, 201, 202, 301, 302, 401)

66.490%
Boise Metro Chamber Boise Chamber Offices

(Units 101, 102, 203)

5.025%
Condo Board Meetings
Last Meeting/Report Next Meeting Next Report Due
January 3, 2022 TBD TBD
Issues/Comments: