Agency Wide – All Districts Project Update
December 9, 2022Parking & Mobility |
Boise Bike Share 2.0: The Agency Board approved a sponsorship agreement for the Bike Share 2.0 pilot program at the June Board meeting. Valley Regional Transit launched the pilot program starting with 50 bikes on July 13. From July 13 through August 31, users have taken 1,256 rides on the bikes. Through the September 1 deadline for matching sponsorships, Valley Regional Transit has secured $25,000 in sponsorships from other organizations. Project Lead: Matt Edmond
ParkBOI – Garage Stairwell Handrails: Cascade Enterprises will be removing out of compliance handrails and cable guards and refabricating, painting, and reinstalling new ones in the 9th & Main, 10th & Front, Capitol & Main, Capitol & Myrtle Garages, Removal and fabrication of the hand and guardrails completed at the Capitol & Main, 9th & Main garages. Idaho street side tower painting of the rails is in progress and will be complete the first week of December. Minor Fabrication of the handrails, guardrails has begun at the Capitol & Myrtle garage, the project will reach Substantial completion by December 7, 2022. The project contract amount is $406,000. Project Lead: Aaron Nelson
421 N 10th St Property: The Agency has an agreement with the Carpark to monitor the lot starting in November. Project Lead: Aaron Nelson
City GO: Formerly known as the Downtown Mobility Collaborative, the downtown’s Transportation Management Association is up and running. This partnership of Valley Regional Transit, City of Boise, ACHD Commuteride, Boise State University, St Luke’s Hospital, Downtown Boise Association, and CCDC involves marketing its transportation products and services to the downtown community. The CCDC Board approved a renewed Memorandum of Understanding for City Go at its October 2020 meeting. In response to a request from VRT, the Agency has included a $60,000 contribution to City Go in the proposed FY2022 budget for CCDC. An overview is located at citygoboise.com. Project Lead: Matt Edmond
10th & Front Garage Structural Concrete Repairs Phase 2
The Agency will seek board approval at the December meeting to award the contract to Consurco, the lowest bidder of the received four bids on this project. The scope of work consists of partial depth repairs on level four across the entire length of the beams, removal/replacement of concrete, installation of anodes and removal/replacement of any damaged rebar with epoxy coated rebar. The Agency’s budget includes sufficient funds for the project and the contract amount is $790,997. Project Lead: Aaron Nelson
Condominium Associations |
Building Eight Condominiums Association
CCDC Contact: Aaron Nelson |
||
Member | Unit | Percent Interest |
CCDC | Capitol & Myrtle Parking Garage (Unit 2) | 35% |
Raymond Management | Hampton Inn & Suites (Unit 1) | 62.5% |
Hendricks | Retail Units (Units 3 & 4) | 2.5% |
Condo Board Meetings | ||
Last Meeting | Next Meeting | Next Report Due |
December 20, 2021 | December 2022 | December 31, 2022 |
Issues/Comments: |
Front Street Condominium Association
CCDC Contact: Aaron Nelson |
||
Member | Unit | Percent Interest |
CCDC | 9th & Front Parking Garage | 25.76% |
GBAD | 2.00% | |
Aspen Condominiums | Aspen Lofts | 52.17% |
Hendricks | BoDo Retail Units | 20.07% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
September 20, 2022 | TBD | November 30, 2023 |
Issues/Comments: | Annual meeting held. Sarah from EPR will be having roof work done on one of the stair towers to prevent water from infiltrating the tower. |
U.S. Bank Plaza Condominium Association
CCDC Contact: Matt Edmond |
||
Member | Unit | Percent Interest |
LN City Center Plaza/ Clearwater Analytics | A, 1A, 1B, 1C, 1H, 1K, 1L, 2C, 3C, 5A, 6A, 7A, 8A, 9A | 77.372% |
CCDC | 1F, 1G, 1J, 2B, 4B, 5B | 6.861% |
GBAD | 4A | 3.040% |
Boise State University | 1D, 1E, 2A, 3A, 3B | 6.131% |
Valley Regional Transit | B1, B2, B3 | 6.429% |
Sawtooth Investment Mgmt
|
10A | 0.167% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
July 23, 2021 | October 17, 2022 | August 2022 |
Issues/Comments: |
Capitol Terrace Condominium Association
CCDC Contact: Aaron Nelson |
||
Member | Unit | Percent Interest |
CCDC | Capitol & Main Parking Garage | 50% |
Hawkins Companies | Main + Marketplace | 50% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
October 25, 2022 | TBD | October, 2023 |
Issues/Comments: | Stairwell work to be completed by December 2022. Fire inspection contract with JCI finalized. |
Downtown Parking Condominiums Association
CCDC Contact: Aaron Nelson |
||
Member | Unit | Percent Interest |
CCDC | 9th & Main Parking Garage | 93.51% |
Les Bois Holdings, LLC | Commercial, Main Street side | 2.03% |
Eastman Building, LLC | Commercial, Idaho Street side | 4.46% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
September 28, 2022 | TBD | September 30, 2023 |
Issues/Comments: | The annual meeting was held, and all parties were notified that the waterproofing project is now complete. The Handrails guardrails replacement project is currently going on and anticipated to be completed in December. |
ACME Fast Freight Condominium Association
CCDC Contact: Matt Edmond |
||
Member | Unit | Percent Interest |
CCDC | 11th & Front Parking Garage, 30.1%
(Units 402, 403, 501, 502) |
28.485% |
Ball Ventures Ahlquist | 11th & Front Parking Garage, 69.9%
(Units 104, 015, 201, 202, 301, 302, 401) |
66.490% |
Boise Metro Chamber | Boise Chamber Offices
(Units 101, 102, 203) |
5.025% |
Condo Board Meetings | ||
Last Meeting/Report | Next Meeting | Next Report Due |
January 3, 2022 | TBD | TBD |
Issues/Comments: |