Rebuild Capitol Boulevard Blocks
Boise River to Myrtle Street

Construction Update (as of December 24, 2024):

The next phase of construction for the Rebuild Capitol Boulevard Blocks: Boise River to Myrtle Project has begun. This phase focuses on the critical replacement of the water main and geothermal lines, which increases capacity for future growth, ensuring long-lasting reliability, cleaner drinking water, and renewable energy for Downtown Boise businesses and residents.

Important Things to Know:

  • There will be a two-lane road closure along the work area to give construction crews ample space and safety to make these important improvements.
  • The sidewalk on the west side of Capitol Boulevard from The Cabin north to Myrtle Street will be closed. A pedestrian detour will be marked with signs.
  • Business access is open to FedEx Office, Treasure Valley Ink, Nomad Beverage Company, The Gas Lantern Drinking Company, White Dog Brewing, and Jackson’s Food Stores. Sidewalk closures will be phased to allow access at all times during construction.
  • Access to the parking lot off of Fulton Street north of White Dog Brewing will remain open from Capitol Boulevard.
  • Pedestrian access to The Cabin and Greenbelt from the west side of Capitol Boulevard will reopen around January 6, 2025.

 

Pedestrian Detour (as of December 24, 2024):

 

Project Overview

Downtown Boise is experiencing significant growth, leading to changes in how people travel through the area and how public rights-of-way are utilized. Recognizing the evolving needs of our community, CCDC has initiated the Capitol Boulevard Streetscape Improvements Project to address these opportunities and elevate the downtown experience. This project is an integral part of our broader program dedicated to constructing streetscapes that foster a network of pedestrian-friendly streets and contribute to the unique identity of the downtown area.

 

Improvements From the Boise River to Myrtle Street Include:

Pedestrian Upgrades:

  • Upgraded ADA-accessible sidewalks, crossings, and ramps
  • Detectable warning signals at pedestrian ramps
  • Extension of protected bike lanes and the city’s bike way network
  • New Valley Regional Transit hub

Streetscape Enhancements:

  • Additional street trees and plantings
  • Historic-style street lighting
  • Replacement of irrigation system and stormwater facilities
  • Addition of bike racks, benches, and trash cans

Utility Upgrades:

  • Replacement of geothermal line
  • Veolia water line replacement
  • Updated pedestrian signal at River Street
  • New pedestrian signal at Fulton Street

 


Project Background

The Capitol Boulevard Streetscape Improvements Project is driven by a commitment to adapt and enhance downtown spaces in response to the dynamic growth experienced by Boise. By investing in these enhancements, CCDC aims to create a more welcoming, functional, and visually appealing environment for residents, visitors, and businesses alike. The project aligns with our vision for a downtown that reflects the evolving needs and aspirations of the community, fostering a sense of place and identity.

 

Project Timeline

  • Spring 2024: Final Design for Improvements Approved
  • Summer 2024:  Permitting
  • Fall 2024: Construction Begins
  • Spring 2025: Anticipated Project Completion

 

Contact 

CCDC project manager, Megan Pape, is overseeing this project.