Place Making Project Update: Freak Alley & Union Block Alley – CCDC Alley Program
March 14, 2018CCDC and City of Boise are working with property owners and managers to improve Freak Alley and Union Block Alley as public spaces. Boise planning staff will manage an urban design process with a stakeholder group (including ownership interests), followed by final design and construction to be managed by CCDC.
The sewer work was completed in February. CCDC Board will consider GMP #2, which covers the alley work, at the March 12 Board meeting. If approved, work will begin in Freak Alley in late March and conclude in Union Alley in mid-June.
For more information, please visit the Freak Alley & Union Block Alley project page.