News Media Center

30th Street URD Projects Update

August 9, 2021

News & Notes

News Update on CCDC Projects in the 30th Street URD

Formed in December 2012, the 30th Street URD runs along 27th Street, Whitewater Park Boulevard and encompasses the West Main Street and Fairview Avenue corridor.

 

Economic Development

186 S Whitewater Park Blvd – Corner Gem / North 27th and West Main Mixed Use: Roundhouse has submitted a Type 3 application for a project at this 186 South Whitewater Park Boulevard that includes over 150 apartments and 15,000 square feet of commercial and retail space. The developer would also build a North 28th Street extension connecting Main Street and Fairview Avenue through the property. The developer plans future phases that will potentially add apartments, transportation connectivity, structured parking and commercial spaces. The developer anticipates beginning road work in fall 2022.  Project Lead: Alexandra Monjar

901 N 27th Street – 27th Street Crossing – PP Type1: The Board approved a Type 1 agreement in May 2021 for this mixed-use project located at the northeast corner of N. 27th Street and Stewart Ave. The project will include 65 apartments and 6,000 square feet of ground-floor commercial space. Eligible Expenses would include improvements to stormwater facilities, sidewalks with trees and landscaping, alley improvements and public art. Site preparation work has begun and completion is expected in June 2022.  Project Lead:  Alexandra Monjar

2850 W Fletcher Street –  27th and Fairview Apartments: The Agency is in discussions with developer KAL Pacific & Associates for Type 2 assistance for its planned residential and commercial mixed-use project located at 27th Street and Fairview Avenue. The project contemplates two, seven-story, mixed-use apartment buildings with 358 total units and ground floor retail space and parking, and a four-story office building. The developer plans to extend Fletcher Street to Fairview Avenue, which was proposed in the ACHD Fairview and Main Local Streets Plan and connect the greenbelt to both streets. The project received Design Review approval in May 2021. Project Lead: Alexandra Monjar

Mobility

Main and Fairview Transit Stations and Platforms:  The City of Boise, Valley Regional Transit and CCDC are redesigning and constructing improvements at six bus stops along Main St and Fairview Ave between Whitewater Park Blvd and N 16th Street.  After no bids were received in response to a formal invitation to bid in April, Agency staff negotiated a contract directly with Wright Brothers, which the CCDC Board then approved at its June 14 Board meeting. Construction is anticipated to start later this summer.  Project Lead: Amy Fimbel

2525 W Fairview – St. Luke’s Transit Station – PP Type 4: The construction of St. Luke’s project on 27th and Fairview overlaps with CCDC’s Main and Fairview Transit Stations and Platforms project. The Agency is negotiating with St. Luke’s to finalize a Type 4 Participation Agreement for the construction of this platform following the Board’s designation in June 2021. Project Lead: Alexandra Monjar