News Media Center

Westside District – Projects

May 5, 2023

News & Notes

Click to Enlarge
Economic Development

9th and Bannock Streets Intersection Geothermal Repairs – Type 4 Partnership with Boise City:  This partnership with the City of Boise will provide upgrades to its geothermal system adjacent to the intersection of 9th & Bannock Streets. The Agency is working with Public Works Engineering to help fund the geothermal upgrade costs, not to exceed $250,000. The Board approved the T4 Agreement on February 14, 2022. The project is complete. Project Lead: Karl Woods

1721 W. Idaho St. – The Martha – Agency-Owned Property: The Agency negotiated a Disposition and Development Agreement with SMR Development LLC as approved at its July 12, 2021, Board Meeting. In accordance with the terms of the Agreement, the sale of the property closed on October 15, 2021. The Developer worked with Surel’s Place to select artist Laurel Rau to create the building’s mural, whose concept was approved by the Board on August 8, 2022. The project was completed in February 2023 and is actively leasing. The Agency is reviewing cost documentation for reimbursement. Project Lead: Alexandra Monjar

Block 68 Catalytic Redevelopment Project: At its December 2021 meeting, the Board selected Edlen & Company’s proposal for the disposition of Agency owned property at 1010 W. Jefferson Street and 421 N. 10th Street through a competitive Request for Proposals (“RFP”) process and approved the Agreement to Negotiate Exclusively (“ANE”) with the Developer in March 2022 and its First Amendment in October 2022. The Disposition and Development Agreement (“DDA”) for the Workforce Housing Project on Block 69 North is predicated on a land exchange with the YMCA of Agency-owned property at 421 N 10th St for the YMCA’s property on Block 69 N. The Agency and YMCA executed the Land Exchange Agreement in July 2022 and the Amended and Restated Land Exchange in October 2022, at which time the Board also approved the Block 69 N DDA. The Board approved the Block 68 South DDA for disposition of 1010 W Jefferson St at its December 2022 meeting. The Developer is working on completing due diligence and Schematic Design, and the Agency expects to present an update on each project at the Board’s May meeting. Project Lead: Alexandra Monjar

1010 W. Jefferson St. – 10Ten Building – Agency Owned Property: McAlvain Construction Companies will be using 60 parking spaces for staging items for Rebuild 11th Street Blocks, as well as using a small office space on the second floor for a construction field office. All leases expire in May 2023, and the building will become vacant. No significant maintenance items to report. Project Lead: Amy Fimbel/ Aaron Nelson

1700 W. Main St. – Rock Hard Granite Renovation – PP Type 1: Approval of the final Agreement for this commercial building renovation occurred in February and demolition has begun. The Developer is working through final permitting with the City of Boise, and the expected completion date is TBD. Project Lead: Kevin Holmes

1110 W. Grove St. – Renegade Hotel – PP Type 4: The Agency continues its coordination with Hendricks Commercial Properties on the streetscape and infrastructure improvements as part of the Linen Blocks on Grove Street and Rebuild 11th Street Blocks projects with the planned development of this 7-story, 122-key boutique hotel. The Board designated the project for Type 4 Capital Improvement Project Coordination participation in May, and its Type 4 Agreement was approved by the Board in September. Project Lead: Alexandra Monjar

1015 Main St. – Smith Block Building – PP Type 1: This restoration project includes extensive facade renovation work sensitive to the historic nature of the building. The first-floor retail space will be renovated with the exterior of the building into a new bar. The Developer is seeking Type 1 assistance to reimburse for restoration costs associated with the facade renovation, including replacing windows, historically accurate awnings, and new storefront display windows and entry doors. The Board approved the final Type 1 Agreement at its January 11, 2023, meeting, and construction is underway. Project Lead: Kassi Brown

1522 W. State St. – 16th & State – PP Type 2: Developer Johnson & Carr is constructing a seven-story mixed-use building with 104 residential units and 1,600 square feet of ground-floor retail on the site of an old gas station. The project includes workforce housing with 10 percent of the units reserved for rent-restricted, income-qualified residents. Public improvements eligible for CCDC reimbursement include streetscapes along 16th and State Streets. Utility upgrades include water line relocations and stormwater management infrastructure. Total Development Costs are estimated at $25 million, and Eligible Expenses at $657,655. The project is requesting the use of CIP funds dedicated to housing developments which are to be completed before the expiration of the Westside District. The Board approved the final agreement in March and construction is anticipated to begin this summer. Project Lead: Kevin Holmes

120 N. 12th St. – 12th & Idaho – PP Type 2: The Board designated this 26-story mixed-use development on the corner of 12th and Idaho Street(s) at its January 2023 meeting. The Agency expects to request approval of a Type 2 General Assistance agreement with 12th and Idaho Owner LLC, a joint venture between White Oak Realty Partners, Ponsky Capital Partners, and Oppenheimer Development Corp. in May. Project Lead: Alexandra Monjar

Infrastructure

“Rebuild 11th Street Blocks” – Redevelopment of the 11th Street Corridor – State Street to Grove Street:  This project combines the installation of bikeway infrastructure with streetscape improvements to realize plans by the City and ACHD for 11th Street as a corridor that prioritizes cyclists, pedestrians, retail business, and residents while accommodating existing vehicular use. The project spans two URDs, with the improvements extending into RMOB with the continuation from Grove Street to River Street. ACHD’s bikeway facility improvements for 11th Street from Heron Street to State Street are under construction and are anticipated to be complete by the end of summer 2023. To maximize public investment, the Agency entered into an Interagency Agreement with ACHD to include in the project scope ACHD’s planned pavement rehabilitation, stormwater upgrades, and the replacement of the underground Boise City Canal Bridge crossing on 11th Street. Jensen Belts Associates lead the design effort, and McAlvain Construction Companies is the Construction Manager/General Contractor (CM/GC). Construction started in June 2022. Project Lead: Amy Fimbel

State Street Streetscape & Fiber-Optic Conduit: This is a cost-share project with an ACHD Downtown Boise Implementation Program (DBIP) project to rehabilitate State Street between 2nd & 16th Streets. CCDC-funded improvements include the installation of a fiber-optic conduit bank between 8th and 15th Streets and streetscape improvements between 12th and 14th Streets. Streetscape components include wider sidewalks, street trees, furnishing zones, and suspended pavement systems (Silva cells) for tree root growth and stormwater retention. The project also anticipates green stormwater infrastructure features in the form of bioretention planters and a landscaped median at select locations throughout the project area. CCDC anticipates a Type 4 participation agreement with the City of Boise for landscaping within the bioretention planters and potential landscaped median features between 12th and 14th Streets. ACHD bid on this project in August but rejected all bids due to high pricing. ACHD re-bid the project in January 2023, and bids were again rejected. The ACHD Commission has asked its design team to re-examine the western portion of the project design from 8th to 14th Street for ways to improve safety for bike and pedestrian modes. Agency continues to coordinate with ACHD and development teams associated with YMCA and Block 68/69. Project Lead: Zach Piepmeyer

Bannock Street Streetscape Improvements, 12th to 16th Streets: This project will make streetscape improvements on both sides of Bannock St. between 12th and 16th Streets to improve pedestrian connectivity from the West Downtown neighborhood into downtown. The design will be coordinated with ACHD’s Bannock Street Neighborhood Bikeway project. In March 2023, a competitive RFQ process resulted in CCDC selecting CSHQA as the project’s design professional. The design is anticipated to be completed in spring 2024 with construction to start later that same year. Project Lead: Amy Fimbel

Mobility

8th Street Improvements, State to Franklin Streets:  This project will improve mobility and safety between the North End Neighborhood and Boise State University. The proposed 8th Street bike facilities will connect to a future east west ACHD Franklin Street Bikeway, and ACHD is leading a companion project to extend 8th Street bike facility improvements north of Franklin Street to Union Street. The CCDC project proposes undergrounding overhead power and telecommunication lines as well as streetscape and transit improvements along the frontage of several properties. The ACHD Commission adopted a modified Concept A as the preferred alternative for the CCDC section (State to Franklin) and for the ACHD section of the project (Franklin to Union). The Board approved Task Order 19-006 for final design services with Kittelson & Associates at its March 2023 Meeting and final design work is underway. Design anticipated to be complete in early 2024 with construction beginning spring 2024. CCDC anticipates use of the Construction Manager/General Contractor (CM/GC) model for construction of the project. Project Lead: Zach Piepmeyer